ARTICLE 7
NEW CONSTRUCTION  - SERIES 7000
7000
General Policy Statement
7015.1
Parent Involvement
7053
Performance, Labor and Material Payment Bonds
7110
Determining Needs
7112(a),(b)
Forecasting Enrollments
7113(a),(b)
Evaluating Existing Buildings
7114(a),(b)
Determining Extent of New Construction
7115(a),(b),(c),(d),(e)
Developing Education Specifications
7120
Patterns of Participation
7121
Involving the Staff
7122(a),(b)
Involving the Public
7123
Using Educational Consultants
7132(a),(b)
Administration of Individual Projects
7133(a),(b)
Services of School Attorney
7140
Relations with the Public
7150
Relations with other Governmental Units
7151
Relations with State Governmental Agencies
7152
Relations with Federal Governmental Units
7210
Architectural and Engineering Services
7214
Engineer
7222
Acquisition
7343
Final
7353
Final Payments to Contractors
7415
Receiving and Opening of Bids
7431
Justification of Change Order
7453(a)
Clerk-of-the-Works
7453(b)
Responsibilities and Duties
7520
Inspection of Completed Project
7542
Recording Names of Board Members, Administration, Architects, or Builders
7000 

New Construction

General Policy Statement

Providing for proper school plant facilities is a major responsibility of the board and the
district administration.  The design of the school plant, adequacy of space, and flexibility
of use, all combine to affect the instructional program.

Since school construction is costly and buildings when constructed become a permanent
part of the community to be used by large numbers of people, great care must be taken
to be sure that the facilities will be appropriately designed for best use both now and in
the future.  

Policy adopted:  January, l975
Policy reaffirmed:  January, l995


7110

New Construction
Determining Needs

The significance of providing school facilities that enhance the district's educational
program is recognized by the board.  To assure a comprehen-sive approach to
projecting and planning needs, at least the following aspects of need will be considered:

1. The expanding and changing educational program of the district

2. Relations with the total community and projected developments in
 those relationships over the years

3. Plant and site aesthetics as they affect the education of pupils and
 the feelings of people about their schools

4. The changing make-up of our population as to age distribution,
 educational levels, and the like

5. Community planning and zoning

6. The financial ability of the school district

7. The safety and welfare of pupils

8. The relationship between the projected new facilities and those
 already in existence

9. True economy reflecting full value for each tax dollar expended

The superintendent is directed to establish such administrative arrangements as he may
consider necessary to determine such need.  In so doing, he may draw upon a wide
range of resources, including the area utility, commercial, industrial, and governmental
entities, as well as the district staff and educational consultants.

Policy adopted:  January, l975
Policy reaffirmed:  January, l995   


7112(a)

New Construction

Forecasting Enrollments

Enrollment forecasts shall be prepared under the direction of the superintendent,
utilizing current enrollment information supplemented with data furnished by the county
planning office.

Policy adopted:  January, l975
Policy reaffirmed:  January, l995


7112(b)

New Construction

Forecasting Enrollments

Methods for forecasting enrollment shall consist of the following:

1. Public facility plan projections

2. Periodic student census

3. Principals' reports for current and projected enrollment

4. Review and evaluation of proposed rezoning

5. Review of approved building permits

6. Information submitted by builder and developers

7. Reports indicating anticipated and approved number of dwelling units
 resulting from submitted site plans

Rules approved:  January, l975
Rules reaffirmed:  January, l995


7113(a)

New Construction

Evaluating Existing Buildings

All existing school facilities will be evaluated periodically for their spatial, thermal, visual,
sonic, and aesthetic requirements in terms of the desired educational programming.

In addition to the inspections provided by other district personnel, planning for major
rehabilitation and remodeling will be incorporated in the school facilities master plan on a
scheduled basis.  

Policy adopted:  January, l975
Policy reaffirmed:  January, l995


7113(b)

New Construction

Evaluating Existing Buildings

Procedures in evaluating existing buildings:

1. School principals shall provide periodic reports listing deficiencies noted in their
building

2. Buildings shall be visited and surveyed by the board of education and
administrative staff

3. The administration shall utilize information developed through work-order
summaries of maintenance requests

4. Conferences shall be held with school administrative staff and faculty to discuss
desired improvements

5. Existing buildings should be evaluated concurrently with addition planning to
determine the comparative adequacy of existing facilities to current standards

6. An up-to-date inventory of existing plans shall be maintained in accordance with
school planning regulations.

Rules approved:  January, l975
Rules reaffirmed:  January, l995 


7114(a)

New Construction

Determining Extent of New Construction

The extent of new construction shall be determined by the increase in enrollment, by
adopted pupil-teacher ratios, by changing educational programs, by the condition of
existing facilities, and within the present and projected budgetary limitations.  

Policy adopted:  January, l975
Policy reaffirmed:  January, l995


7114(b)

New Construction

Determining Extent of New Construction

1. Size, capacity, and number of buildings shall be determined by the enrollment, both
current and anticipated.

2. Enrollment information shall be obtained from county agencies, and the school
administration.

3. Educational program shall be prepared and translated into the architectural
program.

4. Special and community use of facilities shall be considered and provided for to the
extent approved by the board.

5. New construction shall be provided when modification or expansion of existing
facilities is not feasible.

6. Changes or additions may result from revised pupil-teacher ratios.
 
Rules approved:  January, l975
Rules reaffirmed:  January, l995


7115(a)

New Construction

Developing Education Specifications  

To insure that facilities being planned have a design best suited to implementing the
educational program, the superintendent will provide for the establishment of
educational specifications that will apply in the planning and building of school facilities.

The educational specifications will include at least the following:

1. Description of the pupils to be housed (e.g., age level, level of
 intelligence,
physical normality or abnormality)

2. The kinds of educational activities to be carried on (e.g., vocational heavy
emphasis on typing, or science, or rehabilitation)

3. The kinds and quantities of furniture and equipment needed

4. The relationships among areas of plant and site (e.g., band room and library;
playing fields and locker rooms; front office and general school control)

5. Special site consideration of aesthetics, traffic patterns, cooperative community
use, and the like

6. Any other kinds of unique information that will give guidance to an architect  

Policy adopted:  January, l975
Policy reaffirmed:  January, l995


7115(b)

New Construction

Developing Education Specifications

Educational specifications are written after consultation and study with committees of
teachers, administrators, consultants, maintenance technicians, and citizens.  Upon
completion, specifications are reviewed by the faculty members affected by the
specifications, presented to the board, and then presented to the architect.

Generally, the content of a set of educational specifications would include all or part of
the following items:

I. A statement of the educational philosophy as it pertains to the
 specific construction project

II. Community and school characteristics:

 A. The plan of organization and expected enrollments of the school
 
  1.  Grade levels
  2.  Maximum expected enrollments, with trends and projections,
   if necessary

 B. The construction plan for this facility:
 
  1. An addition, complete unit, expandable unit, or a phased
   program leading to a complete facility

 C. Special services to be provided:

  1. Guidance programs
  2. Social workers' programs
  3. Provision for exceptional children
  4. Others


7115(c)

New Construction

Developing Education Specifications  (continued)

 D. Special provision for community use:

  1. Cooperative park, school arrangements
  2. Parent-Teacher Associations
  3. Community athletic programs
  4. Civil Defense
  5. Others

 E. The extent to which the adult educational program will use this
 facility.  Provisions to be made to implement this program.

 F. The extent to which the student will be transported and the
  facilities required to handle this service adequately.

 G. Cafeteria services to be provided and the maximum number likely
  to be served.

 H. The policy regarding multiple use of spaces.

 I. Other pertinent data relating to the project.

III. Site characteristics:

 A. Site considerations to be made for this project
  1. Site size and location defined
  2. Recommended building orientation:
   a.  Service drives
   b.  Parking requirements for staff, students, and public
   c.  Sidewalk and other approaches
   d.  Outside lighting


7115(d)

New Construction

Developing Education Specifications  (continued)  

IV. Requirements of the physical plant

 A. Instructional spaces required:
 
  1. The elementary school:  Each space to be described by
   a.  Number of spaces required
   b.  Floor area needed
   c.  Location in respect to other facilities
   d.  Activities requiring special type of construction

  2. The secondary school:  A statement of instructional purpose is
   to precede the description of each specialized area.  Each
  classroom space is identified by :
   a.  Number of spaces required
   b.  Floor area needed
   c.  Location in respect to other facilities
   d.  Special construction requirements for certain facilities
    (soundproofing, additional ventilation, etc.)

 B. Non-instructional spaces required (elementary and secondary):
  1. Each page to be identified
  2. Number of facilities required
  3. Floor area requirements

 C. Orientation of spaces:
  1. Relationship between instructional and non-instructional
  spaces
  2. Relationship of spaces to site
  3. Interrelationship between instructional areas 


7115(e)

New Construction

Developing Education Specifications  (continued)

 D. Environmental controls:
  1. Lighting quantity and quality
  2. Acoustical properties and noise control
  3. Aesthetic qualities interior and exterior
  4. Heating and/or cooling
  5. Ventilation
  6. Properties of the floor, wall and ceiling finishes
  7. Color--in certain instances
  8. Safety requirements

 E. Additional information or comments necessary to further
  interpret the educational program into an efficient school
  building  

Rules approved:  January, l975
Rules reaffirmed:  January, l995 


7120

New Construction

Patterns of Participation

Educational programs are neither unchanging nor simple to incorporate into a facility
plan.  Anticipation of program change makes flexible buildings necessary, so that the
period of "updatedness" is extended.  At the same time, it is necessary to accommodate
the existing program.  The natural interest of parents, the professional interest of
educators, the public relations interest of the board, the neighborhood development
interest of local residents, and the varied interest of many others both complicate the
program and challenge the abilities of all concerned with school planning.

The school construction program must represent the cooperative endeavors of many
people.  Its success is a measure of the ability of many functionaries to cooperate.  No
single person or group isolated from the overall educational process can satisfactorily
design a school building that is intended to the enhance the instructional program of
others.  Organization and communication in planning school facilities are tantamount to
success.

To insure that the school construction program proceeds as smoothly and rapidly as
possible, the following step-by-step process for planning and building shall be utilized.
Generally speaking, a school construction program involves four broad phases:

1.  Identifying school building needs

2.  Planning the school plant

3.  Constructing the building

4.  Accepting and using the plant.

Policy adopted:  January, l975
Policy reaffirmed:  January, l995


7121

New Construction

Patterns of Participation Involving the Staff

When the school district contemplates new construction or remodeling, the employee
organizations shall be advised.  When the proposed construction pertains to an existing
school, up to three members of the planning committee will be appointed by the
respective employee organizations from the staff of that school.  When the proposed
construction is for a new school or other building, up to three representatives of the
planning committee will be appointed by the employee organizations.

Policy adopted:  January, l975
Policy reaffirmed:  January, l995


7122(a)

New Construction

Involving the Public

New educational programs, proposed new construction, and/or innovations in
educational methods shall be discussed in public at regular board meeting and/or with
local citizen groups or selected committees.

Policy adopted:  January, l975
Policy reaffirmed:  January, l995


7122(b)

New Construction

Involving the Public

1. Committees may be appointed by the board to study specific areas of
 educational interest or planning.

2. Meetings shall be scheduled as necessary to permit the public to
 present views on matters affecting the particular community or
 school.

3. The administrative staff shall be available on request to supplement   the
board during public presentation of matters involving educational
 planning.

4. Visual aids (drawings, sketches, rendering, models, maps, charts, and
 other statistical presentations) shall be provided for use at public
 meetings.

Rules approved:  January, l975
Rules reaffirmed:  January, l995


7123

New Construction

Using Educational Consultants

The board recognizes the complexities of providing physical facilities in a rapidly growing
community.  This responsibility is complicated by the demands for change made by a
dynamic educational program.

Consultants and other appropriate resource personnel from state agencies, colleges,
universities, planning laboratories, and consulting firms may be used to augment school
system personnel, when needed and authorized by the superintendent of schools.

Policy adopted:  January, l975
Policy reaffirmed:  January, l995


7132(a)

New Construction

Administration of Individual Projects

Planning Checklist for the Development of Individual Projects

1. Determine educational philosophy
2. Determine educational program
3. Identify facility needs
4. Assign priority to each need by school and by total school district
5. List priority needs
6. Visit school and determine extent of work listed
7. Meet with architect, principal, and others at school
8. Select site (if necessary)
9. Program:
 a. Site
 b. Budget
 c. Spaces
 d. Equipment
10. Have staff revise educational specifications
11. Review revised educational specifications with superintendent and
 consultants
12. Make progress report to area supervisors
13. Examine preliminary drawings
14. Let principal and consultants review preliminary drawings
15. Revise preliminary drawings
16. Have preliminary drawings reviewed by:
 a. State education department and/or state fire marshall
 b. City fire marshall
 c. School board representative (informal)
 d. School board (formal)
17. Revise educational specifications to emerging plans
18. Make progress reports to area supervisors
19. Have working drawings developed
20. Review working drawings
21. Revise working drawings


7132(b)

New Construction

Administration of Individual Projects (continued)

22.  Have working drawings reviewed by:
 a.  State department and/or state fire marshall
 b.  City fire marshall
 c.  Fire underwriters
 d.  School board representative (informal)
23.  Obtain approval by school board (formal)
24.  Have detailed drawings developed
25.  Review and revise detailed drawings
26.  Obtain state department approval (formal)
27.  Prepare contract
28.  Put contract out for bids
29.  Receive bids
30.  Awards bids
31.  Start work or break ground
32.  Work
 a.  1/4 complete
 b.  1/2 complete
 c.  3/4 complete
d.  complete
33.  Make preliminary inspection
34.  Occupy project
35.  Hold dedication
36.  Make final inspection
37.  Accept construction  (formal action by school board)

Rules approved:  January, l975
Rules reaffirmed:  January, l995  


7133(a)

New Construction

Services of School Attorney

The services of the school attorney shall be available for legal counseling on matters
pertaining to site acquisition, easements, dedication, contracts, contract payments, liens
or claims, and such other matters as may arise.
 
Policy adopted:  January, l975
Policy reaffirmed:  January, l995


7133(b)

New Construction

Services of the School Attorney

1. The school board attorney shall review:
 a.  land purchase contracts.
 b. construction contracts.
 c. easements and/or permits for utilities.
 d. title and deeds for dedicated sites.
 e. the need for new legislation relative to special land use.

2. The attorney shall prepare:
 a. titles and deeds.
 b. settlement documents for land transfer.
 c. condemnation documents for site and easement acquisition.
 d. liens and claims.
 e. deeds of dedication for right-of-way.
 f. resolutions for board approval involving easements, rights-of-way,
 and land sales.

3. The attorney shall provide legal representation during condemnation
 proceedings, suits involving construction contracts and payments.

4. The attorney shall coordinate settlement and condemnation payments
 for land and easement acquisition.  

Rules approved:  January, l975
Rules reaffirmed:  January, l995


7140

New Construction

Relations with the Public

The board accepts its responsibility for keeping the public informed as to the use of
bond funds for school facilities.

The office of the superintendent will provide informative news releases through mass
media organs or by other means, as the superintendent deems necessary and desirable.

Policy adopted:  January, l975
Policy reaffirmed:  January, l995


7150

New Construction

Relations with other Governmental Units

The board will work with state and federal agencies as prescribed by law, and will in
addition cooperate with all governmental units in order to provide the best school
facilities while obtaining the greatest efficiency and economy in the use of the tax dollar.  

Policy adopted:  January, l974
Policy reaffirmed:  January, l995


7151

New Construction

Relations with State Governmental Agencies

The board maintains and advocates cooperative relations with all state governmental
agencies in the planning of educational facilities.

Policy adopted:  January, l974
Policy reaffirmed:  January, l995


7152

New Construction

Relations with Federal Governmental Units

Cooperative relations will be maintained with federal governmental units to explore
areas of mutual benefit in planning improved educational facilities.  

Policy adopted:  January, l974
Policy reaffirmed:  January, l995


7210

New Construction

Architectural and Engineering Services

The board of education will screen architectural applications and interview firms that
apparently will meet the school district needs as developed by the school staff and
citizens committee.  The board of education will then select the architect or architectural
firm to serve the district.

Policy adopted:  January, l974
Policy reaffirmed:  January, l995


7214

New Construction

Engineer

The board shall employ certified engineers, at approved fee, to perform professional
services for projects of limited scope involving planning design or study in specialized
fields, such as site development, plumbing, heating, air conditioning, structural,
foundations, electrical, communications, and others.

Legal Reference:   R.R.S. 81-855  Engineers and architects; public buildings; supervision by registered engineer o architect required; exception. 79-443  District board; schools; supervision and control. 48-433  Building plans; duty of draftsman; violation; penalty

Services

The services provided by the engineer shall be

1. to develop appropriate designs for the required facilities within the
 budget of the board.
2. to prepare feasibility studies of specialized systems.
3. to provide consulting services on technical matters, or in support of   legal
proceedings or public hearings.
4. to be responsible for all technical services included in the owner-
 engineer agreement.
5. to render such other services requested by the board within the scope
 of an agreement.

Fees

The engineer's fee shall be established by the board based on the type of services to be
rendered and conditions involved.

Policy adopted:  January, l995


7222

New Construction

Acquisition

Property acquisition for school purposes shall generally proceed in the following manner:

1. The property shall be appraised at current market value by two
 competent appraisers.

2. Negotiations with the owner on the basis of the appraisals shall be   made.

3. The purchase shall be consummated or condemnation proceedings shall  be
instituted.  

Legal Reference:   R.R.S. 79-4, 107  Eminent domain; power of the district to exercise. 79-4, 114  Eminent domain; amount and character of land authorized to be taken. 79-543  Real estate for future sites outside district; acquire, own, manage, hold, erect buildings on, when; annexation; effect.

Policy adopted:  January, l995


7343

New Construction

Final

Final payment for architectural and/or engineering services may be rendered only after
the project has been certified by the architect and/or engineer as completed and the
project has been formally accepted by the board of education.  

Policy adopted:  January, l995


7353

New Construction

Final Payments to Contractors

Prior to final payment the contractor furnishes:

1. Five (5) copies of a report which lists the names of materials and
 manufacturers used on the project.

2. As-built drawings (2 complete sets).

3. Building location and as-built topographic survey prepared by
 registered engineer and certified correct.

Prior to approval of final payment, owner requires a statement of compliance to be
provided by the architect, stating that the building and site work are complete and
approved in accordance with the approved plans and specifications.

Policy adopted:  January, l995


7415 

NEW CONSTRUCTION 

Procedures—Bidding Construction Projects

The District shall bid every project for the construction, remodeling, or repair of any school-owned building or for site improvements when the contemplated expenditures for such project are forty thousand dollars or more. The bidding procedures shall comply with the requirements of state law and shall include the following:

1. Notice to Bidders: The Administration shall prepare a notice to bidders containing a general description of the scope of the project being bid; the location of the project; the means of obtaining project documents, including plans and specifications; the date and hour bids will close; and the date, hour and place bids are to be returned, received and opened, and a provision that such bids will be immediately and simultaneously opened in the presence of the bidder, or representatives of the bidders, when the hour is reached for the bids to close.

2. Regular Manner of Advertisement for Bids: The notice to bidders for any project shall be published one time in a newspaper of general circulation in the School District. The notice shall be published at least seven (7) days prior to the date designated for the opening of such bids. The Board of Education or Administration may, in its sole discretion, elect to utilize further advertisement for bids as it may determine appropriate to secure a sufficient number of qualified bidders for the scope of the project.

3. Bid Opening: When the hour is reached for such bids to close, bids will be immediately and simultaneously opened in the presence of the bidder, or representatives of the bidders.

4. Additional Procedures. Labor and material bonds in the amount of the contract shall be provided by the person to whom the contract is awarded in a sum not less than the contract price, except for projects with a total cost of five thousand dollars or less, unless required by the bid notice or contract documents. Each bid for which a labor and material bond is required shall be accompanied by a bid bond or certified check in the amount of five percent (5%) of such bid. The Board of Education or Administration may provide for additional procedures for the procurement, opening and acceptance of bids as deemed appropriate for a particular project.   

Legal Source: Neb. Rev. Stat. §73-101 et seq.; Neb. Rev. Stat. §73-106; Neb. Rev. Stat. §52-118
Adopted: July 12, 2004.


7431

New Construction

Justification of Change Orders

The board of education or its agent may make changes in the scope of the work
required to be performed by the contractor by making additions or omissions without
invalidating the contract, without relieving or releasing the contractor from any
obligations under the contract or any guarantee given pursuant to the contract
provisions, without affecting the validity of the guaranty bonds, and without relieving or
releasing the surety of sureties of the bonds.  All such work shall be executed under the
items of the original contract unless expressly provided otherwise.

If applicable unit prices are not contained in the agreement, the architect shall, before
ordering the contractor to proceed with desired changes, request and itemized proposal
covering the work involved in the change after which the procedure shall be as follows:

A. If the proposal is acceptable the architect shall prepare the change   order
for acceptance by the contractor;

B. Each change order shall include in its final form:
 1. A detailed description of the change in the work;
 2. The contractor's proposal (if any) or a conformed copy;
 3. A definite statement as the resulting change in the contract
 price and/or time;
 4. The statement that all work involved in the change shall be
  performed in accordance with contract requirements except as
 modified by the change order.

C. No extra work shall be done nor any obligation incurred for payment   except
upon a written order fully signed by the owner's representative  and
approved by the board of education.  Such order shall state the   cost of
such extra work will be provided by the district.

Policy adopted:  January, l995


7453(a)

New Construction

Clerk-of-the-Works

The board may provide supervision through a building inspector (Clerk-of-the-Works) on
a continuous or intermittent basis, depending on the size of the project, as required by
state regulations.

Policy adopted:  January, l995


7453(b)

New Construction

Clerk-of-the-Works:  Responsibilities and Duties

The clerk-of-the-works shall be responsible to the superintendent and the board for the
supervision of all new building construction.  Specific duties are as follows:

1. To supervise daily all board construction work in progress.

2.  To coordinate the work of the general contractor and other
 contractors
to facilitate the progress of the construction.

3. To inspect all construction as it progresses, with authority to stop work of any kind
pending a final decision of the architect and board.

4. To work with architect, board, and contractors to insure full compliance of the plans
and specifications.

5. To cooperate and assist the maintenance department in the operation of facilities
due to the knowledge and experience obtained during the installation and operation
of the equipment during construction.

6. To act as liaison member between local officials, fire department, building and
plumbing inspectors.

7. To initiate, schedule and examine installation of electric, gas and water utility
services.

8. To recommend and advise board with respect to equipment, services and facilities
to be incorporated in new construction.

9. To study review continuously new construction methods, procedures, materials and
installations to insure practical, economical results in planning new facilities.

Rule approved:  January, l995


7520

New Construction

Inspection of Completed Project

Completed projects shall be inspected in accordance with the contract for architectural
and/or engineering services.  Administrative staff inspections shall include those
conducted by the superintendent of schools, the business manager or the building
principal.  Recommendations shall be made for the acceptance of the building or
facilities to the board by the architect and/or engineer and the superintendent of schools.

Acceptance of the completed project by the board of education will not be made until the
board in official session has toured the facilities with the architect and/or engineer and
the superintendent of schools.
 
Policy adopted:  January, l995


7542

New Construction

Recording Names of Board Members, Administrators, Architects, or Builders

All major building projects will be identified by a suitable plaque(s)
identifying the project, year completed, the names of the board members,
superintendent and the architectural firm.

Policy adopted:  January, l995


Series 0000 | Series 1000 | Series 2000 | Series 3000
Series 4000 | Series 5000 | Series 6000 | Series 7000 | Series 9000